Page 1 of 1

1" Extension at FLLS

Posted: Sun Apr 20, 2008 4:28 pm
by Mike Walsh
I hope I'm not too out of line in posting these photos of the progress of the new 1" extension at the Finger Lakes Live Steamers.

on April 20th, 2008, we installed a bridge at the club site. It was needed to move forth on our extension.

photos are below:

http://www.pbase.com/mrw5390/flls&page=all

Our hope is to have the extension complete by the end of summer! I would estimate there's approximately 500' to 1000' of track remaining to be installed, along with two turnouts.

Regards,
Mike Walsh

FFLS

Posted: Sun Apr 20, 2008 7:23 pm
by Steve Bratina
Keep up the good work. I must say though, I certainly miss going down to your club to run my 3/4" stuff.